• About
  • Join the Co-op / Donate
  • Contact
Tuesday, August 4, 2026
Subscribe
No Result
View All Result
The Brief
NB POD
NB MEDIA CO-OP
Events
Share a story
  • Articles en français
  • New Brunswick
  • Canada
  • World
  • Environment
  • Indigenous
  • Labour
  • Gender
  • Politics
  • Culture
  • Videos
  • NB debrief
  • Articles en français
  • New Brunswick
  • Canada
  • World
  • Environment
  • Indigenous
  • Labour
  • Gender
  • Politics
  • Culture
  • Videos
  • NB debrief
No Result
View All Result
NB MEDIA CO-OP
No Result
View All Result
Home Energy

Auditor General questions NB Power’s $3.55-billion gas plant deal

by Bruce Wark
June 2, 2026
Reading Time: 4min read
A person wearing a clear rain poncho holds a megaphone and a sign reading 'Stop the Tantramar Gas Plant — Clean Air, Clean Water, Clean Energy for All,' standing on a dirt road in overcast, rainy conditions.

Hudson Rogers speaks at a May Day rally against the proposed Tantramar gas plant on May 1, 2026, near Centre Village. Photo: Bruce Wark

Headshot of New Brunswick Auditor-General Paul Martin, wearing a black blazer and plaid tie, smiling against a dark grey background.
New Brunswick Auditor-General Paul Martin. Photo: Auditor-General’s report

New Brunswick Auditor General Paul Martin issued a report today accusing NB Power of pushing ahead with its proposed gas/diesel generating plant near Centre Village without fully weighing the costs and risks to its customers or considering possible alternatives.

The report also notes that NB Power’s agreement with PROENERGY requires the U.S. company to establish a financial, equity partnership with Indigenous communities, yet the Auditor General found during his investigation that no such partnership had been reached.

The report adds that last December, NB Power amended the agreement to allow PROENERGY to withdraw from the project and recover its costs if it does not form a partnership with Indigenous communities by mid-2026.

The Auditor-General’s report discloses financial details that were kept confidential during hearings before the Energy & Utilities Board.

Using NB Power’s own figures, the Auditor General calculated that its partnership with PROENERGY would cost roughly $3.55 billion over 25 years.

The report cites NB Power figures showing that if the utility owned and operated the project itself, its costs would be between $425 and $700 million lower.

Financial risks

The Auditor General suggests that NB Power faces substantial financial and contractual risks including:

  • having to make full monthly payments to the U.S. company even when the gas/diesel plant cannot generate electricity for reasons outside NB Power’s control
  • paying for fuel whether or not it is burned
  • bearing “construction schedule risks associated with delays in the delivery of equipment without financial remedy.”

The Auditor General also criticizes NB Power for treating its agreement with PROENERGY primarily as a supply arrangement rather than a 25-year capital investment.

“As a result, the project did not proceed through the full Investment Governance Framework (IGF) in the way expected for a major capital commitment,” the report says.

It also notes that the agreement with PROENERGY initially required the company to pay NB Power $46 million in US dollars as a “performance assurance payment” to offset construction risks.

“The performance assurance payment was due on August 1, 2025, but was not paid to NB Power,” the report says.

“An amendment to the Agreement was subsequently approved and dated December 31, 2025 to reduce the immediate security requirement to USD $10 million, with the full USD $46 million becoming payable only upon satisfaction of specified conditions. As a result, NB Power’s contractual leverage to enforce PROENERGY’s compliance with construction milestones and the agreed upon schedule was significantly weakened.”

Risks and benefits of alternatives

While the Auditor General accepts NB Power’s forecast that it would need an additional 400 MW of generating capacity by August 1, 2028, his report says the utility did not conduct a rigorous assessment of the risks and benefits of alternatives to dual-fuel combustion turbines until after it had signed an agreement with PROENERGY.

The report refers to NB Power’s list of possible alternatives in its planning documents including:

  • battery storage
  • biomass conversion
  • demand response
  • imported power
  • intermittent renewables (wind, solar)
  • small modular nuclear reactors

In a response included in the report, NB Power said it faced an urgent risk of winter electricity shortages and argued that delays could have increased the likelihood of blackouts.

The utility also disputed some of the Auditor General’s conclusions, saying the partnership model transferred significant construction and performance risks to PROENERGY.

To read the Auditor General’s report and NB Power’s response, click here.

Bruce Wark worked in broadcasting and journalism education for more than 35 years. He was at CBC Radio for nearly 20 years as senior editor of network programs such as The World at Six and World Report. He currently writes for The New Wark Times, where this story first appeared on June 2, 2026.

Tags: Auditor Generalbattery storageBruce WarkCentre Villageelectricitynatural gasNB PowerPROENERGYrenewable energyTantramar Gas Plant
Send

Related Posts

Mitton says community will not accept proposed gas plant on Chignecto Isthmus
Indigenous

Indigenous financial stake not essential for Tantramar gas plant: NB Power executive

July 16, 2026

NB Power Vice President Brad Coady says that a 500 megawatt gas and diesel plant near Centre Village could go...

NB Power launches rebate program for landlords’ energy upgrades, prompting questions from housing rights advocates
Energy

NB Power launches rebate program for landlords’ energy upgrades, prompting questions from housing rights advocates

July 15, 2026

NB Power has announced a new program that will provide rebates to landlords who invest in energy efficiency upgrades in...

Gas plant opponents line Sackville bridge saying fight isn’t over
Energy

Gas plant opponents line Sackville bridge saying fight isn’t over

July 10, 2026

About 120 demonstrators waved to passing traffic on the TransCanada highway and on Sackville’s Main Street Thursday in the latest...

‘People’s MOU’ called on feds to change course on climate policy ahead of pipeline announcement
Energy

‘People’s MOU’ called on feds to change course on climate policy ahead of pipeline announcement

July 3, 2026

Climate scientists reported record-breaking ocean surface temperatures in June amid a deadly heatwave in Europe, while Canadians experienced record heat...

Load More

Recommended

Student accepted into UNB grad program remains trapped in Gaza one year after applying for Canadian student visa

Grad student association cites ‘privacy reasons’ for silence about Palestinian scholar trapped in Gaza

5 days ago
La résistance ça se célèbre : L’École libre de Tracadie

La résistance ça se célèbre : L’École libre de Tracadie

4 days ago
Photos: Between the colours, and the continuation of war

Photos: Between the colours, and the continuation of war

6 days ago
NB Media Co-op

© 2019 NB Media Co-op. All rights reserved.

Navigate Site

  • About
  • Join the Co-op / Donate
  • Contact
  • Share a Story
  • Calendar
  • Archives

Follow Us

No Result
View All Result
  • About
  • Join the Co-op / Donate
  • Contact
  • Events
  • Share a Story
  • NB POD
  • COVID-19
  • Videos
  • New Brunswick
  • Canada
  • World
  • Arts & Culture
  • Environment
  • Indigenous
  • Labour
  • Politics
  • Rural

© 2019 NB Media Co-op. All rights reserved.

X
Did you like this article? Support the NB Media Co-op! Vous avez aimé cet article ? Soutenez la Coop Média NB !
Join/Donate